The first steps of this lesson
Step 1: Set Up the Test Before You Backfill
The 2025 Caltrans Standard Specifications, section 20-2.01A(4)(b)(i), require a pressure test for leakage on irrigation supply lines, run in the Engineer's presence on business days from 8 a.m. to 5 p.m. unless authorized. The test is done before backfilling the supply line trench, with the system gate valves open and the open ends of the supply line and fittings plugged or capped. You must notify the Engineer at least 48 hours before the test. A new supply line connected to an existing line must be isolated from it and tested on its own.
Step 2: Method A: 125 psi, 1 Hour, 5 psi Drop
Method A (section 20-2.01A(4)(b)(ii)) starts with a pressure gauge calibrated from 0 to 200 psi in 5 psi increments and accurate to within 2 psi. Fill the supply line with water, connect the gauge, and bring the line to a pressure of 125 psi. Remove the source of pressure and leave the line under that pressure for 1 hour, with the gauge staying in place until the period is over. If the gauge shows a drop of more than 5 psi, locate and repair the leaks, then repeat the 1-hour test until the drop is 5 psi or less.
The remaining 3 steps, the worked example and the quiz are in the course. This is a preview. The full lesson, with the step-by-step explanations, a worked example and a quick-check quiz, is inside the classroom.
Independent exam preparation. Contractors Classroom is not affiliated with the Contractors State License Board, and no course can guarantee a passing result.