The first steps of this lesson
Step 1: The Lab Sets the 100 Percent
Before fill goes down, the soils lab runs a moisture-density test on the actual soil. The curve gives two numbers: Maximum Dry Density (MDD, in pounds per cubic foot) and Optimum Moisture Content (OMC, in percent). The 2025 California Building Code words it this way in section 1804.6: "maximum dry density at optimum moisture content determined in accordance with ASTM D1557." The MDD is defined as 100 percent. Every field test is then reported as a percentage of that number, called relative compaction (RC). The Caltrans Standard Specifications (section 6-2.01A) say relative compaction is tested under California Test 216 or 231.
Step 2: Know the Percentage the Spec Requires
The percentage comes from the project documents. For shallow foundations on compacted fill, 2025 CBC section 1804.6 says the fill must comply with an approved geotechnical report; the exception is fill 12 inches or less in depth, which needs an in-place dry density not less than 90 percent of the ASTM D1557 maximum dry density, verified by special inspection under section 1705.6. Caltrans earthwork is 95 percent relative compaction in the zones listed in section 19-5.03B (for example the top 0.5 foot below the grading plane between the outer edges of shoulders) and 90 percent in other embankment areas (section 19-5.03C). Each layer of aggregate base must reach at least 95 percent (section 26-1.03E). Always read the grading plan and soils report first - they set the number for your job.
The remaining 3 steps, the worked example and the quiz are in the course. This is a preview. The full lesson, with the step-by-step explanations, a worked example and a quick-check quiz, is inside the classroom.
Independent exam preparation. Contractors Classroom is not affiliated with the Contractors State License Board, and no course can guarantee a passing result.