The first steps of this lesson
Step 1: Build to the Amended Text
CFC 903.3.1.1 requires sprinklers per NFPA 13 as amended in Chapter 80, 905.2 requires standpipes per NFPA 14 as amended in Chapter 80, and 507.2.1 requires private fire service mains per NFPA 24 as amended in Chapter 80. The California changes are printed in CFC Chapter 80 under each standard, and they are the text you install to. NFPA 25 for inspection and testing is referenced as the 2013 California edition, and Title 19, California Code of Regulations, Chapter 5 governs the label put on each system riser after the authority having jurisdiction accepts the system.
Step 2: The Hydraulic Design Information Sign
The installing contractor identifies a hydraulically designed system with a permanently marked weatherproof metal or rigid plastic sign secured with corrosion-resistant wire, chain or other approved means, placed at the alarm, dry pipe, preaction or deluge valve supplying that area (NFPA 13 29.4.1 as amended). A pipe schedule system gets a sign saying so and listing the hazard classifications. The sign (29.4.3) lists, among 14 items: the location of the design areas, discharge densities, required flow and pressure at the base of the riser and at the water supply source, occupancy or commodity classification and maximum storage height, the hose stream allowance included, the installing contractor, flow and pressure at the pump discharge where a pump is installed, sprinkler type, orifice size, K-factor and SIN, and the edition of NFPA 13 used. A system with floor control valves needs a sign at each floor control valve (16.9.3.1.3.4).
The remaining 3 steps, the worked example and the quiz are in the course. This is a preview. The full lesson, with the step-by-step explanations, a worked example and a quick-check quiz, is inside the classroom.
Independent exam preparation. Contractors Classroom is not affiliated with the Contractors State License Board, and no course can guarantee a passing result.