The first steps of this lesson
Step 1: A Pit Absorbs Through Its Sidewall
Section H 301.1(4) of 2025 CPC Appendix H says the effective absorption area of a seepage pit is the excavated sidewall area below the inlet, not counting any hardpan, rock, clay, or other impervious formation. The required area still comes from the tank capacity or flow (whichever is greater) and the soil factor in Table H 201.1(2), the same as for a leach field. That means a pit that passes through a clay layer only gets credit for the porous layers.
Step 2: Why Percolation Testing Matters
Section H 401.1 says seepage pit sizes shall be computed by percolation tests unless the AHJ approves using Table H 201.1(2). Tight soil needs more sidewall: a clay site asks for 90 or 120 square feet per 100 gallons instead of 40, so the pits must be deeper or there must be more of them. The CSLB C-42 study guide poses this same question, and the answer is "deeper or more pits might need to be installed."
The remaining 3 steps, the worked example and the quiz are in the course. This is a preview. The full lesson, with the step-by-step explanations, a worked example and a quick-check quiz, is inside the classroom.
Independent exam preparation. Contractors Classroom is not affiliated with the Contractors State License Board, and no course can guarantee a passing result.