Caltrans Concrete: Slump Limits, Free Water and Delivery Time
"Caltrans Concrete: Slump Limits, Free Water and Delivery Time" is lesson 6 of 7 in the Concrete (C-8) Learning Hub. It opens with "Where This Applies" and works through 5 short steps, then a worked example you can check yourself against.
One-time purchase, no subscription. Law & Business included.
Steps in this lesson
Where This Applies
Slump Limits by Type of Work
Free Water Cap
Delivery Time and Revolution Limits
Adding Water at the Delivery Point
The worked example in the course applies this lesson to a realistic job in 5 steps, from "Free-water cap" through "If withheld water is added".
What you'll be able to do
Explain the main idea of "Caltrans Concrete: Slump Limits, Free Water and Delivery Time" in plain language you can use on the exam.
Apply this step with confidence: "Free Water Cap".
Apply this step with confidence: "Delivery Time and Revolution Limits".
Apply this step with confidence: "Adding Water at the Delivery Point".
Test yourself on the worked example and the quick-check quiz inside the classroom.
The diagram for this lesson, exactly as it appears in the Learning Hub.
The first steps of this lesson
Step 1: Where This Applies
The 2025 Caltrans Standard Specifications, Section 90 Concrete, govern concrete on work whose contract includes them, such as Caltrans projects. The building codes tell you what the structure needs; Section 90 tells you how the delivered concrete is controlled, and on a job that includes it the printed numbers are the contract.
Step 2: Slump Limits by Type of Work
90-1.02G(6) regulates mix water so that slump (tested under ASTM C143 as the spec names it) or penetration (California Test 533) falls in a nominal range. Reinforced concrete structures with sections over 12 inches thick: nominal slump 1 to 3 inches, maximum 5. Sections 12 inches thick or less: nominal 1 to 4, maximum 6. Concrete placed under water: nominal 6 to 8, maximum 9. CIP concrete piles: nominal 5 to 7, maximum 8. Concrete pavement and nonreinforced members are controlled by penetration only. If the result exceeds the nominal range, adjust later batches; do not use a batch that exceeds the maximum.
The remaining 3 steps, the worked example and the quiz are in the course. This is a preview. The full lesson, with the step-by-step explanations, a worked example and a quick-check quiz, is inside the classroom.