General Building (B) · Lesson 6 of 7

Scheduling and Coordinating Subs

"Scheduling and Coordinating Subs" is lesson 6 of 7 in the General Building (B) Learning Hub. It opens with "Sequential vs. Overlapping Work" and works through 5 short steps, then a worked example you can check yourself against.

One-time purchase, no subscription. Law & Business included.

Steps in this lesson

  1. Sequential vs. Overlapping Work
  2. Finding a Finish Date From a Sequence
  3. Overlapping Trades: Use the Longest One
  4. Building the Full Timeline
  5. Why This Matters for the Bid

The worked example in the course applies this lesson to a realistic job in 5 steps, from "Add the phases together" through "Convert to a finish date".

What you'll be able to do

  • Explain the main idea of "Scheduling and Coordinating Subs" in plain language you can use on the exam.
  • Apply this step with confidence: "Building the Full Timeline".
  • Apply this step with confidence: "Why This Matters for the Bid".
  • Test yourself on the worked example and the quick-check quiz inside the classroom.
SCHEDULING AND COORDINATING SUBS Sequential work adds; overlapping work takes the longest one Framing (sequential) 6 days Electrical rough-in 4 days Plumbing rough-in 5 days ← sets the pace (overlap uses longest) Drywall (sequential) 5 days 16 working days total (6 + 5 + 5) THE TWO RULES + Sequential trades: ADD durations One must finish before the next can start. max Overlapping trades: use the LONGEST They start together; only the slowest one delays the next phase. CC
The diagram for this lesson, exactly as it appears in the Learning Hub.

The first steps of this lesson

Step 1: Sequential vs. Overlapping Work

Some trades MUST happen strictly in order (rough electrical and plumbing have to finish before drywall closes the walls up) - that's sequential work, and their durations simply add together. Other trades can run in parallel once their own prerequisites are met (electrical rough-in and plumbing rough-in can often happen at the same time, both after framing) - that's overlapping work, and only the LONGER of the two adds to the schedule, not both.

Step 2: Finding a Finish Date From a Sequence

For strictly sequential trades, add up every trade's duration in working days, then count that many working days forward from the start date (skipping weekends, or whatever days aren't worked) to land on the finish date.

Step 3: Overlapping Trades: Use the Longest One

When two or more trades run at the same time inside the same window, that window's length in the schedule is set by whichever trade takes longest - not by adding all of them together. Finishing the shorter trades early doesn't shrink the schedule; only the longest parallel task does.

The remaining 2 steps, the worked example and the quiz are in the course. This is a preview. The full lesson, with the step-by-step explanations, a worked example and a quick-check quiz, is inside the classroom.

More lessons for this trade

Browse all lesson previews

Ready to practice for real?

Try the real classroom free, no sign-up, or get the full course for your trade.

Independent exam preparation. Contractors Classroom is not affiliated with the Contractors State License Board, and no course can guarantee a passing result.