The first steps of this lesson
Step 1: Sequential vs. Overlapping Work
Some trades MUST happen strictly in order (rough electrical and plumbing have to finish before drywall closes the walls up) - that's sequential work, and their durations simply add together. Other trades can run in parallel once their own prerequisites are met (electrical rough-in and plumbing rough-in can often happen at the same time, both after framing) - that's overlapping work, and only the LONGER of the two adds to the schedule, not both.
Step 2: Finding a Finish Date From a Sequence
For strictly sequential trades, add up every trade's duration in working days, then count that many working days forward from the start date (skipping weekends, or whatever days aren't worked) to land on the finish date.
Step 3: Overlapping Trades: Use the Longest One
When two or more trades run at the same time inside the same window, that window's length in the schedule is set by whichever trade takes longest - not by adding all of them together. Finishing the shorter trades early doesn't shrink the schedule; only the longest parallel task does.
The remaining 2 steps, the worked example and the quiz are in the course. This is a preview. The full lesson, with the step-by-step explanations, a worked example and a quick-check quiz, is inside the classroom.