Steps in this lesson

  1. Who Section 5.508.2 Covers
  2. Piping Rules That Reduce Leaks
  3. Valves, Relief Devices and Receivers
  4. The 300 psig Standing Pressure Test
  5. The Three-Stage Evacuation

The worked example in the course applies this lesson to a realistic job in 6 steps, from "First pressure test" through "Minimum timed holds".

What you'll be able to do

  • Explain the main idea of "Supermarket Leak-Tight Installation: CALGreen 5.508.2 Pressure Test and Evacuation" in plain language you can use on the exam.
  • Apply this step with confidence: "Valves, Relief Devices and Receivers".
  • Apply this step with confidence: "The 300 psig Standing Pressure Test".
  • Apply this step with confidence: "The Three-Stage Evacuation".
  • Test yourself on the worked example and the quick-check quiz inside the classroom.
Leak-Tight Check: Pressure Test and Vacuum HoldsSEQUENCE AND HOLD TIMES (5.508.2.5, .6)Pressure test300 psig, 24 h, +/- 1 lb1st vacuum1,000 microns, 30 min2nd vacuum500 microns, 30 min3rd vacuum300 microns, 24 h, drift 100Bars are not to scale. Minimum timed holds:24 h + 0.5 h + 0.5 h + 24 h = 49 hLOG CHECKStart 300.0 psig; after 24 h 298.6 psigChange 1.4 lb > 1 lb: FAILRepair leak, retest, same gaugeAfter 24 h: 299.4 psigChange 0.6 lb: PASS3rd vacuum starts at 290 micronsAfter 24 h: 360 micronsDrift 70 ≤ 100 microns: PASS410 microns (drift 120) would FAILPull-down time and repairs are extraRetest and evacuation pass: 49 hours of timed holdsEvacuate after the pressure test and before charging (5.508.2.6)WHO AND WHAT IS COVERED (5.508.2)New systems, retail food stores 8,000 sq ft or more, remote compressors or condensing unitsHigh-GWP refrigerants only (GWP 150 or greater); ammonia and CO2 are named low-GWP exceptionsSource: 2025 California Green Building Code Sections 5.508.1, 5.508.2, 5.508.2.5, 5.508.2.6CC
The diagram for this lesson, exactly as it appears in the Learning Hub.

The first steps of this lesson

Step 1: Who Section 5.508.2 Covers

2025 CALGreen Section 5.508.2 applies to new commercial refrigeration systems in retail food stores of 8,000 square feet or more of conditioned area that use refrigerated display cases or walk-in coolers or freezers connected to remote compressor units or condensing units. New includes both new facilities and replacement of existing systems. It applies to high-GWP refrigerants, those with a GWP of 150 or greater. Low-GWP refrigerants under 150, such as ammonia and carbon dioxide, are the stated exception. Section 5.508.1 separately bars HVAC, refrigeration and fire suppression equipment containing CFCs or halons.

Step 2: Piping Rules That Reduce Leaks

Piping must comply with the California Mechanical Code and be accessible for leak protection and repair (Section 5.508.2.1). Threaded pipe, copper tubing under 1/4 inch OD, flared connections and short-radius elbows are not used, with these exceptions: threaded connections at the compressor rack; tubing under 1/4 inch OD in systems of 5 pounds of refrigerant or less, clamped to a rigid base to keep vibration below 8 mils; double-flared connections for pressure controls, valve pilot lines and oil; and short-radius elbows only where space prohibits long-radius elbows.

The remaining 3 steps, the worked example and the quiz are in the course. This is a preview. The full lesson, with the step-by-step explanations, a worked example and a quick-check quiz, is inside the classroom.

More lessons for this trade

Browse all lesson previews

Ready to practice for real?

Try the real classroom free, no sign-up, or get the full course for your trade.

Independent exam preparation. Contractors Classroom is not affiliated with the Contractors State License Board, and no course can guarantee a passing result.