Step 1: Where the Vent Must End
Relief devices that discharge outside the refrigeration system must be arranged to discharge outside the building (2025 CMC Section 1112.11.2). The point of discharge must be not less than 15 feet above the adjoining ground level, except that outdoor Group A1 systems may discharge at any elevation if the point is in an access-controlled area for authorized personnel. It must also be not less than 20 feet from windows, building ventilation openings, pedestrian walkways or building exits. The end must not spray onto people or let debris into the pipe, and a vertical-up vent subject to moisture needs a drip pocket at least 24 inches long, sized as the vent pipe, with a valve or drain plug.
Step 2: Rules for the Vent Pipe and Valve
The discharge pipe may not be smaller than the outlet of the relief device or fusible plug (Section 1112.12.2). No stop valve may sit between a relief device and the parts it protects (Section 1112.7), and the device connects directly to the vessel above the liquid level, accessible for inspection (Section 1112.8). Pipe on a fusible plug or rupture member must be arranged so it cannot plug when the device operates (Section 1112.12.1). Vessels of 10 cubic feet or more discharging to the atmosphere use rupture members or dual relief valves with a three-way valve (Section 1113.6).
The remaining 3 steps, the worked example and the quiz are in the course. This is a preview. The full lesson, with the step-by-step explanations, a worked example and a quick-check quiz, is inside the classroom.
Independent exam preparation. Contractors Classroom is not affiliated with the Contractors State License Board, and no course can guarantee a passing result.