CSLB C-10

Electrical Contractor License Exam Prep (C-10)

Getting ready for the California electrical contractor license exam (CSLB C-10)? Study with 502 practice questions in 5 categories and 6 Learning Hub lessons, made for electricians, with the Law and Business exam included.

One-time purchase, no subscription. Law & Business included.

Diagrams from the C-10 electrical contractor lessons: Lockout/Tagout and Working on Energized Equipment, Temporary Power: GFCIs and the Assured Grounding Program, Voltage Drop with CEC Chapter 9 Table 8 and Working Space and Dedicated Space at Panels
502practice questions
5categories
6Learning Hub lessons
$249Law & Business included

What the exam covers: Electrical (C-10)

The CSLB exam for the California electrical contractor license (C-10) is a closed-book, multiple-choice test. CSLB's official study guide divides it into five major sections and gives each an approximate weight: Planning and Estimating (about 28%), Rough Wiring (about 27%), Finish Wiring and Trim (about 11%), Startup, Troubleshooting, and Maintenance (about 16%), and Safety (about 18%).

Planning and Estimating carries the most weight, about 28%, so it deserves roughly that share of your study time, with Rough Wiring next at about 27%.

Contractors Classroom turns that outline into 502 practice questions in 5 categories (Planning and Estimating, Rough Wiring and Distribution, Finish Wiring and Equipment, Low Voltage and Specialty Systems, and Safety), plus 6 Learning Hub lessons with diagrams (such as "Lockout/Tagout and Working on Energized Equipment" and "Temporary Power: GFCIs and the Assured Grounding Program"). Law and Business, which most applicants take alongside their trade exam, is included at no extra charge.

Exam sections and approximate weights

  • Planning and Estimating~28%
  • Rough Wiring~27%
  • Finish Wiring and Trim~11%
  • Startup, Troubleshooting, and Maintenance~16%
  • Safety~18%

Practice question categories

  • Planning and Estimating57 practice questions
  • Rough Wiring and Distribution160 practice questions
  • Finish Wiring and Equipment111 practice questions
  • Low Voltage and Specialty Systems65 practice questions
  • Safety109 practice questions

What the Electrical Contractor exam covers, section by section

Planning and Estimating (~28%)

Electrical work begins with understanding what already exists and what the project must achieve. The planner examines the current system, reads plans and specifications, and performs load and conductor calculations. Code requirements guide every choice of equipment and material, and projects involving generation or storage need extra attention to how sources interconnect.

  • Surveying existing panels, circuits, and capacity before adding to a system
  • Reading drawings and written specs to determine scope and equipment
  • Sizing conductors, loads, and protection with sound electrical math
  • Applying code rules and choosing materials suited to each installation
  • Planning solar, wind, generator, and battery installations, including stored-energy components

Rough Wiring (~27%)

Rough wiring is the stage where the system takes shape inside walls, ceilings, and equipment rooms. Layouts must keep working space and access around gear, raceways and panels are mounted securely, and conductors are pulled and connected as planned. Grounding and bonding ties it all together for fault safety, including at generation and storage equipment.

  • Laying out circuits and device locations according to the plans
  • Maintaining working space and access around panels and equipment
  • Mounting conduit, boxes, and panelboards, then pulling conductors
  • Connecting metal parts to ground so fault current can travel safely
  • Running wiring for solar arrays, turbines, generators, and battery banks

Finish Wiring and Trim (~11%)

Finish work is where the visible parts go in: receptacles, switches, fixtures, and connections to motors and other equipment. Neat installation, clear identification of circuits and gear, and proper trim plates and sealants make the system safe, serviceable, and tidy. Energy sources and storage equipment receive the same careful final connection and marking.

  • Setting switches, receptacles, and fixtures plumb and securely connected
  • Wiring motors and powered equipment to their controls and disconnects
  • Marking circuits and equipment so others can identify them later
  • Closing up with covers, trim, and sealing material at openings
  • Making final connections for solar, wind, generator, and storage equipment

Startup, Troubleshooting, and Maintenance (~16%)

Energizing a new or repaired system is a controlled step, preceded by inspection and checks. Technicians read meters to confirm voltage, continuity, and insulation condition, then trace symptoms such as dead circuits, tripped breakers, or overheating to their causes. Repairs restore safe operation, and energy-producing systems are watched to see that they perform as designed.

  • Verifying wiring and then bringing circuits to power in a safe sequence
  • Recognizing typical failures like loose connections, overloads, and shorted conductors
  • Finding broken wires or failed parts, then repairing or replacing them
  • Choosing the right meter or tester for each measurement
  • Checking that solar, wind, generator, or battery systems deliver expected output

Safety (~18%)

Electricity can injure instantly, so the trade relies on strict routines. De-energizing and locking out equipment before work, wearing suitable protective gear, and keeping tools in good condition all reduce risk. Crews also must recognize hazardous substances and unusual environments such as wet, dusty, or confined locations, adjusting methods to suit.

  • Isolating power, applying lockout and tagout, and verifying it is dead before touching conductors
  • Wearing rated gloves, eye protection, and head protection for the task
  • Inspecting and using hand tools, ladders, and test equipment properly
  • Handling chemicals and working safely in wet, dusty, or confined spaces

Code books behind the Electrical Contractor exam

The exam outline published for this trade lists these references.

  • 2025 California Building CodeFor an electrician, the building code governs everything the wiring passes through or hangs from: fire-rated walls and floors that need firestopping, accessibility reach ranges that decide device heights, and structural limits on supports. It is the reference behind the plan-reading and code-requirements topics in the Planning and Estimating section.
  • 2025 California Electrical CodeThe core publication of the trade. It sets wiring methods, conductor sizing, overcurrent protection, grounding and bonding, working clearances, special equipment rules, and the chapters on solar, storage and generators. It feeds every section of the exam, most heavily Rough Wiring, Planning and Estimating, and the testing topics in Startup and Troubleshooting.
  • 2025 California Energy CodeThis is where efficiency rules reach the electrician's work: lighting power limits, required controls such as dimmers and automatic shut-off, residential luminaire requirements, and the mandates for solar and batteries on new buildings. It supports Planning and Estimating for design choices and Finish Wiring and Trim for device and control installation.
  • 2025 California Fire CodeThe fire code covers the electrical items that a fire marshal cares about: emergency and standby power, generator and fuel arrangements, stationary storage batteries, rooftop solar access pathways, and fire alarm related work. It is the reference behind energy storage planning and the job site environment topics in the Safety section.
  • American Electricians' HandbookA general trade handbook explaining theory and practice: circuit math, transformers, motors and controllers, wiring diagrams, raceway bending, grounding and tools. Candidates use it to build the fundamentals behind the calculation questions in Planning and Estimating and the motor and equipment installation topics in Finish Wiring and Trim.
  • Photovoltaic SystemsA textbook on solar electric systems: module behavior, series and parallel strings, inverters, charge controllers, batteries, grid-interactive and stand-alone layouts, and commissioning. It is the study source for the energy production and storage bullets that appear inside Planning, Rough Wiring, Finish Wiring, and Startup and Troubleshooting.
  • State of California General Industry & Electrical Safety Orders (Cal/OSHA)Together with the Construction Safety Orders, this Title 8 set governs how electrical work is done safely: who may work on energized parts, de-energizing methods, approach distances to overhead lines, temporary power protection, tools and hazardous materials. It is the reference behind the Safety section, which is about 18 percent of the exam.
  • Ugly's Electrical ReferencesA pocket reference that condenses formulas, conductor and motor tables, box fill, conduit bending data, grounding diagrams and transformer connections. Because the exam is closed book, it is most useful as a model of what a working electrician should know cold, supporting the electrical calculations bullet in Planning and Estimating and the diagnostic topics in Startup.

Key terms for the Electrical Contractor exam

AIC rating
The highest fault current a breaker or fuse can open safely without rupturing. A replacement device must match the original in size and amperage, and its interrupting capability must at least equal the fault current available at the panel where it will sit.
Available fault current
The largest short-circuit current the supply could push through a point in the system, shaped by the utility transformer and the impedance of the conductors in between. It decides which interrupting ratings and equipment ratings the installation must use.
Dedicated equipment space
The column of floor-to-ceiling room above and below a panelboard that is reserved for the electrical system alone. Pipes, ducts and unrelated equipment may not occupy it, so future work and heat dissipation are not blocked.
Working space
The clear zone in front of energized equipment, measured in depth, width and headroom, that lets a qualified person operate or service it and step away quickly. It is different from the dedicated space, and large equipment rooms may need doors that swing outward.
Assured equipment grounding conductor program
A written, recorded testing routine for cord sets and receptacles on temporary power. Visual checks and continuity tests at set intervals stand in for GFCI protection, but only if someone is named to run it and the results are kept.
GFCI protection
A device that compares current leaving on the hot conductor with current returning on the neutral and opens within a fraction of a second when a few milliamperes go missing. It protects people from shock at wet locations, outdoors and on temporary power.
AFCI protection
A breaker or outlet that recognizes the electrical signature of dangerous arcing in branch circuit wiring and trips before it ignites insulation or framing. Unlike a GFCI, its job is fire prevention, and it is required in many dwelling living areas.
Voltage drop budget
The limit on how much voltage may be lost between the source and the load, set by the Energy Code and good practice. Long runs, small wire and heavy current all eat into it, so the fix is usually a larger conductor.
Conductor derating
Lowering the allowable current of a wire because it runs through a hot ambient area or shares a raceway with several other loaded conductors. Heat cannot escape as easily, so the same copper must carry less to protect its insulation.
Raceway fill
The share of a conduit's inside cross-section that conductors may take up, with a lower percentage allowed as the wire count rises. It keeps heat down and prevents insulation damage during the pull.
Grounding electrode conductor
The wire that joins the service grounding point to the grounding electrodes, such as ground rods, a concrete-encased electrode or metal water piping. It ties the system to earth to steady voltage and drain lightning and surges.
Equipment grounding conductor
The path that carries fault current from metal enclosures and frames back to the source, so the breaker opens fast instead of leaving a case energized. On a roof array it connects the module frames and mounting hardware.
Bonding jumper
A short conductor that makes sure two metal parts are electrically continuous, such as service enclosures, across expansion fittings or around loose knockouts. It keeps any fault current on a low-resistance path.
Transfer switch
Equipment that moves a load between the utility and a generator or other source while making it impossible for both to feed the circuit together. It is the main defense against sending power back onto the grid.
Back-feed
Unplanned power flowing from a generator, battery inverter or other source into utility lines or a panel believed to be dead. It can injure line crews and damage equipment, and listed interlocks or transfer equipment exist to prevent it.
Megohmmeter
An insulation tester that applies a high direct voltage and reads resistance in millions of ohms. Electricians use it on motor windings, feeders and cable runs to find moisture or aging insulation before energizing.
Clamp-on ammeter
A meter whose jaws close around one conductor to read the current from its magnetic field, with no need to open the circuit. It is the quick way to compare a motor's running current with its nameplate during startup.
Tamper-resistant receptacle
An outlet with internal shutters that open only when both prongs are pushed at once, so a hairpin or key inserted into one slot does nothing. Dwellings and child-focused spaces call for them.
JA8 high-efficacy light source
A residential lamp or integrated luminaire that meets the Energy Code's test for efficacy and for performance at elevated temperature. Recessed downlights and similar fixtures in homes must use this kind of source.

Where to spend practice time for the Electrical Contractor exam

  • Planning, calculations and materialsPlanning and Estimating carries about 28 percent of the exam, and it blends plan reading, code requirements, material choices and arithmetic. Practice conductor sizing with derating, voltage drop on long runs, box and raceway fill, and the purchase math of quantity discounts plus sales tax. Work each problem by hand with a calculator until the steps are automatic.
  • Rough wiring, clearances and groundingAt about 27 percent, Rough Wiring is the second largest section and covers layout, clearances, raceways, panels, wire installation, and grounding and bonding. Sketch a panel with its working and dedicated space, trace a fault path from a metal enclosure to the source, and review which parts of a system must be bonded.
  • Energy production and storage in every sectionPhotovoltaic, wind, generator, battery and capacitor topics are listed inside Planning, Rough Wiring, Finish Wiring and Startup, so they touch most of the exam rather than one block. Compare how each source connects, what disconnecting and labeling it needs, and how a transfer switch prevents back-feed. Review module strings and battery sizing as math problems.
  • Safety around energized partsSafety is about 18 percent of the exam. Focus on qualified-person rules, de-energizing before work, temporary power protection with GFCIs or an assured grounding program, safe tools, and hazardous material and job site environments. Rehearse the correct order of steps to make equipment safe, test it, and restore power, and recall who is responsible for each step.
  • Startup, testing and troubleshootingAt about 16 percent, this section asks you to energize a system, pick the right test instrument and find faulty wiring or components. Match each symptom to a meter: continuity, clamp-on current, insulation resistance, voltage under load. Practice reading what an open neutral, a loose connection or an overloaded circuit would do to readings.
  • Finish wiring, trim and controlsFinish Wiring and Trim is the smallest block at about 11 percent, so its topics are compact and efficient to review. Cover device placement, motor and equipment connections, labeling, sealants, and the Energy Code controls for residential lighting. Drill the difference between dimmers, vacancy sensors and automatic shut-off, and what wire and equipment labels must show.

Scenarios to talk through before the Electrical Contractor exam

  • A look-alike breaker is offeredA branch circuit breaker has failed and the supply house offers a unit that looks identical. Which characteristics of the original do you match, how do available fault current and the AIC rating enter the decision, and what would you verify at the panel before closing the cover and energizing the circuit? Say what you would also record.
  • Temporary power on a new buildFraming crews are plugging saws and lights into temporary receptacles on a new house. Compare GFCI protection with a documented cord-and-receptacle testing routine. Who has to run and record the tests, what would you inspect on the cords, and what changes if the site becomes wet? Name the paperwork that proves the checks were done.
  • Panel beneath a water pipeA plan shows a new panelboard in a hallway closet with a water line running across the ceiling above it. Discuss working space versus dedicated equipment space, what you would measure on site, who must change their work, and what you would say before rough wiring continues. Explain who you would notify and when.
  • Flickering lights at a detached garageLights flicker and a compressor motor strains at a detached garage on a long underground feeder. Think through the voltage drop budget, the conductor size and any derating from hot conduit or crowded raceways. What would you measure under load, and what would you change first? Explain how you would confirm that your change fixed it.
  • Generator plugged into the houseAfter an outage a homeowner wants to power a few circuits by running a portable generator through a cord into a dryer outlet. Explain the danger of back-feed, what equipment would let the circuits run safely, and how you would label and test the arrangement so utility crews are protected. List the paperwork the utility might request.
  • Metal frames on a roof arrayA roof-mounted solar array has metal module frames and rails. Trace how fault current would return to the source, which parts must be bonded, where you would use a bonding jumper, and what continuity checks and labels you would want completed before the system is energized. State the order of your checks and why.
  • A motor that will not startA newly connected pump motor hums and trips, and the owner suspects a bad motor. Put your testing steps in order using a clamp-on ammeter, a megohmmeter and a voltage check under load. What readings would point to wiring, insulation or the supply, and what would you rule out first? Explain how you justify your order of checks.
  • Trim-out in a remodeled living areaYou are finishing a remodeled living room with recessed downlights, a dimmer and new outlets. Which items would you confirm for the high-efficacy light source requirement, the control type, tamper-resistant receptacles and arc-fault protection, and what labels or box details would you check before the inspector arrives? Mention the sequence of inspections you expect.

Learning Hub lessons

Each lesson has guided steps, a diagram, a worked example and a quick check inside the classroom.

Preview the lesson diagrams

  1. Lockout/Tagout and Working on Energized EquipmentSteps: Qualified persons only, and assume it is live; De-energize with a lock and a tag; Test, work, then re-energize in order; If live work is truly unavoidable; Habits that the Safety Orders write down
  2. Temporary Power: GFCIs and the Assured Grounding ProgramSteps: When temporary wiring is allowed; Feeders and branch circuits; Temporary poles; GFCI or assured grounding: the choice; Running the AEGCP
  3. Voltage Drop with CEC Chapter 9 Table 8Steps: What the Energy Code limits; Where the wire resistance comes from; The math (Ohm's law); Adjusting for temperature; Pick the smallest wire that fits the budget
  4. Working Space and Dedicated Space at PanelsSteps: Why the clear space exists; Depth: Table 2340.16 and the CFC floor; Width, headroom and doors; Dedicated space and illumination; Entrances, access and guarding
  5. Residential Lighting Controls and Blank Boxes (Energy Code §150.0(k))Steps: Luminaires must meet JA8; Recessed ceiling downlights; Wall controls, dimmers and automatic-off; Blank electrical boxes; Control devices and outdoor lighting
  6. Standby Power, Generators and Back-FeedSteps: Emergency versus standby timing; How long the power must last; Protecting critical circuits and elevators; Portable generators and back-feed; Maintenance, transfer switch test and records

See the classroom in action

Frequently asked questions

How do I get a California electrical contractor license?

An electrician or electrical contractor who wants to contract independently applies under C-10. CSLB generally requires documented journey-level experience, a bond, and passing scores on both the Law and Business exam and the C-10 exam. Rules change, so confirm them with CSLB.

What does the electrical contractor exam ask about planning and estimating?

Planning and Estimating is the heaviest part of the C-10 exam, at about 28%. Expect questions on surveying existing panels, circuits, and capacity before adding to a system, reading drawings and written specs to determine scope and equipment, and sizing conductors, loads, and protection with sound electrical math. Next in weight come rough wiring (about 27%) and safety (about 18%).

What kinds of questions are on the electrical contractor exam?

The three sample questions in CSLB's C-10 study guide ask about bonding rooftop solar equipment, choosing a replacement circuit breaker, and pricing receptacles with sales tax and a free-item offer. Like every question on the exam, each has four choices and one best answer.

Which codes and books does the C-10 exam reference?

CSLB's C-10 study guide lists the 2025 California Building, Electrical, Energy, and Fire Codes (Title 24), the Cal/OSHA safety orders (Title 8), and trade references such as American Electricians’ Handbook, Photovoltaic Systems, and Ugly’s Electrical References. Use them to study; the exam itself is closed-book.

Is the electrical contractor exam open book?

No. The C-10 study guide says no reference materials may be used, even though it names American Electricians’ Handbook and Photovoltaic Systems among the books to study from. A calculator is provided, and guessing is not penalized.

Can I take the electrical contractor exam outside California?

CSLB's exam FAQ says trade exams are given in California or Oregon only, so C-10 is not offered in other states, although Law and Business can be taken out of state. Check the current PSI list when you schedule.

How are the 502 C-10 practice questions organized?

They are split into 5 categories, largest first: Rough Wiring and Distribution (160), Finish Wiring and Equipment (111), Safety (109), Low Voltage and Specialty Systems (65), and 1 more. Rough Wiring and Distribution holds about 32% of the questions. 6 Learning Hub lessons add diagrams and worked examples for the harder topics. The missed-question review collects every question you get wrong.

Is there a free trial for electrical contractor exam prep (C-10)?

Yes. The free C-10 preview opens the real classroom with no sign-up and gives you the first question from every C-10 category, including Rough Wiring and Distribution and Finish Wiring and Equipment, plus Law and Business. The full course is a one-time $249 purchase.

Is electrical contractor exam prep available in Spanish?

The website and the eight demo videos are available in Spanish. The classroom and the 502 C-10 practice questions are in English for now; translating the questions is not part of the course yet.

Ready to practice for real?

Try the real classroom free, no sign-up, or get the full course for your trade.

Independent exam preparation. Contractors Classroom is not affiliated with the Contractors State License Board, and no course can guarantee a passing result.